In size oriented metrics, metrics are developed based on the _____________________?
Correct answer: C. number of lines of code
- A. number of Functions
- B. number of user inputs
- C. number of lines of code
- D. amount of memory usage
Explanation
Size-oriented metrics use the size of the delivered software as their base, traditionally measured in lines of code. Function points instead measure functionality delivered.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? [email protected]
Practise Software Project Management
171 free Software Project Management MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Software Engineering questions like this
Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.
More Software Project Management questions
A graphical technique for finding if changes and variation in metrics data are meaningful is known as_________________?
Which of the following is an indirect measure of product ?
Which of the following does not affect the software quality and organizational performance ?
The intent of project metrics is_____________________?
Which of the following is the task of project indicators ?
Which of the following is not an information domain required for determining function point in FPA ?