What describes the data and control to be processed ?
Correct answer: B. Software scope
- A. Planning process
- B. Software scope
- C. External hardware
- D. Project complexity
Explanation
The software scope states what data and control the system will process, along with its functions, performance, and constraints. Hardware is an environmental constraint, not a description of the system’s processing scope.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? [email protected]
Practise Requirements Engineering
125 free Requirements Engineering MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Software Engineering questions like this
Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.
More Requirements Engineering questions
A number of independent investigators have developed a team-oriented approach to requirements gathering that can be applied to establish the scope of a project called ?
Which of the following is not one of the five information domain characteristics of Function Point (FP) decomposition ?
Which of the following term is best defined by the statement: "Derive traceability information to maximize information hiding in the design." ?
In the Analysis phase, the development of the ______________ occurs, which is a clear statement of the goals and objectives of the project ?
At which stage of risk analysis specification, the additional security requirements take account of the technologies used in building the system and system design and implementation decisions ?
How many stages are there in Risk-driven requirements specification ?