At which stage of risk analysis specification, the additional security requirements take account of the technologies used in building the system and system design and implementation decisions ?
Correct answer: B. Life-cycle risk analysis
- A. Preliminary risk analysis
- B. Life-cycle risk analysis
- C. Operational risk analysis
- D. All of the mentioned
Explanation
Life-cycle risk analysis considers the technologies, architecture, design, and implementation decisions used to build the system, so it can refine the security requirements accordingly. Preliminary analysis occurs before these details are known, while operational analysis focuses on the deployed system.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? [email protected]
Practise Requirements Engineering
125 free Requirements Engineering MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Software Engineering questions like this
Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.
More Requirements Engineering questions
In the Analysis phase, the development of the ______________ occurs, which is a clear statement of the goals and objectives of the project ?
What describes the data and control to be processed ?
A number of independent investigators have developed a team-oriented approach to requirements gathering that can be applied to establish the scope of a project called ?
How many stages are there in Risk-driven requirements specification ?
Which requirements are the foundation from which quality is measured ?
Which of the following manuals is not a user documentation ?