At which stage of risk analysis specification, the additional security requirements take account of the technologies used in building the system and system design and implementation decisions ?

Correct answer: B. Life-cycle risk analysis

  • A. Preliminary risk analysis
  • B. Life-cycle risk analysis
  • C. Operational risk analysis
  • D. All of the mentioned

Explanation

Life-cycle risk analysis considers the technologies, architecture, design, and implementation decisions used to build the system, so it can refine the security requirements accordingly. Preliminary analysis occurs before these details are known, while operational analysis focuses on the deployed system.

Last updated

Practise Requirements Engineering

125 free Requirements Engineering MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.

Exams that ask Software Engineering questions like this

Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.

Related questions