Ensuring that no more than the allocated number of people are allocated at any given time in Software Scheduling is known as ________________?

Correct answer: B. Effort Validation

  • A. Time Allocation
  • B. Effort Validation
  • C. Defined Milestone
  • D. Effort Distribution

Explanation

Effort validation checks whether the planned allocation of people and effort is feasible, including avoiding over-allocation at any time. Effort distribution concerns spreading work, but the stated constraint is specifically a validation check.