Ensuring that no more than the allocated number of people are allocated at any given time in Software Scheduling is known as ________________?
Correct answer: B. Effort Validation
- A. Time Allocation
- B. Effort Validation
- C. Defined Milestone
- D. Effort Distribution
Explanation
Effort validation checks whether the planned allocation of people and effort is feasible, including avoiding over-allocation at any time. Effort distribution concerns spreading work, but the stated constraint is specifically a validation check.
Last updated
Practise Software Project Management
171 free Software Project Management MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Exams that ask Software Engineering questions like this
Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.
Related questions
A graphical technique for finding if changes and variation in metrics data are meaningful is known as_________________?
A __________ is a measure, an intangible measure, which is difficult to count in clear terms?
A _______________ is developed using historical cost information that relates some software metric to the project cost ?
A listing of the names and addresses of all the employees for an organization would be an example of a(n)_________________________?
A make-buy decision is based on whether________________?