Ensuring that no more than the allocated number of people are allocated at any given time in Software Scheduling is known as ________________?

Correct answer: B. Effort Validation

  • A. Time Allocation
  • B. Effort Validation
  • C. Defined Milestone
  • D. Effort Distribution

Explanation

Effort validation checks whether the planned allocation of people and effort is feasible, including avoiding over-allocation at any time. Effort distribution concerns spreading work, but the stated constraint is specifically a validation check.

Written and checked by , MS Computer ScienceLast updated
Report an error

The more specific you are, the faster it gets fixed. A source beats an opinion.

Prefer email? [email protected]

Practise Software Project Management

171 free Software Project Management MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.

Discussion

Stuck on an option, or know a faster way to get there? Ask or explain it here.

No comments yet. Be the first to explain this one.

Exams that ask Software Engineering questions like this

Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.

More Software Project Management questions