Which of the following is a project scheduling method that can be applied to software development ?
Correct answer: D. Both PERT and CPM
- A. PERT
- B. CPM
- C. CMM
- D. Both PERT and CPM
Explanation
PERT and CPM are both network-based project scheduling techniques that can model task dependencies and timing. CMM is a process-maturity model, not a scheduling method.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? [email protected]
Practise Software Project Management
171 free Software Project Management MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Software Engineering questions like this
Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.
More Software Project Management questions
Ensuring that no more than the allocated number of people are allocated at any given time in Software Scheduling is known as ________________?
Every task that is scheduled should be assigned to a specific team member is termed as_________________?
What is a collection of software engineering work tasks, milestones, and deliverables that must be accomplished to complete a particular project ?
What is used to determine the recommended degree of rigor with which the software process should be applied on a project ?
A technique for performing quantitative analysis of progress is known as______________________?
What is the recommended distribution of effort for a project ?