A technique for performing quantitative analysis of progress is known as______________________?

Correct answer: B. EVA

  • A. BCWS
  • B. EVA
  • C. BAC
  • D. CBSE

Explanation

Earned Value Analysis, or EVA, quantitatively compares planned value, earned value, and actual cost to assess project progress and performance. BCWS and BAC are individual earned-value measures, not the overall analysis technique.