A project usually has a timeline chart which was developed by_________________?

Correct answer: A. Henry Gantt

  • A. Henry Gantt
  • B. Barry Boehm
  • C. Ivar Jacabson
  • D. None of the mentioned

Explanation

The timeline or bar chart used for project scheduling is the Gantt chart, developed by Henry Gantt. Boehm and Jacobson are associated with software engineering models and methods, not this chart.

Written and checked by , MS Computer ScienceLast updated
Report an error

The more specific you are, the faster it gets fixed. A source beats an opinion.

Prefer email? [email protected]

Practise Software Project Management

171 free Software Project Management MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.

Discussion

Stuck on an option, or know a faster way to get there? Ask or explain it here.

No comments yet. Be the first to explain this one.

Exams that ask Software Engineering questions like this

Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.

More Software Project Management questions