A project usually has a timeline chart which was developed by_________________?

Correct answer: A. Henry Gantt

  • A. Henry Gantt
  • B. Barry Boehm
  • C. Ivar Jacabson
  • D. None of the mentioned

Explanation

The timeline or bar chart used for project scheduling is the Gantt chart, developed by Henry Gantt. Boehm and Jacobson are associated with software engineering models and methods, not this chart.