A project usually has a timeline chart which was developed by_________________?
Correct answer: A. Henry Gantt
- A. Henry Gantt
- B. Barry Boehm
- C. Ivar Jacabson
- D. None of the mentioned
Explanation
The timeline or bar chart used for project scheduling is the Gantt chart, developed by Henry Gantt. Boehm and Jacobson are associated with software engineering models and methods, not this chart.
Last updated
Practise Software Project Management
171 free Software Project Management MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Exams that ask Software Engineering questions like this
Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.
Related questions
A graphical technique for finding if changes and variation in metrics data are meaningful is known as_________________?
A __________ is a measure, an intangible measure, which is difficult to count in clear terms?
A _______________ is developed using historical cost information that relates some software metric to the project cost ?
A listing of the names and addresses of all the employees for an organization would be an example of a(n)_________________________?
A make-buy decision is based on whether________________?