How many levels are present in CMM ?
Correct answer: C. five
- A. three
- B. four
- C. five
- D. six
Explanation
The original Capability Maturity Model has five maturity levels: Initial, Repeatable, Defined, Managed, and Optimizing. These levels describe the maturity of an organization's software process.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? [email protected]
Practise Software Project Management
171 free Software Project Management MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Software Engineering questions like this
Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.
More Software Project Management questions
Which of the following is not a typical environment in communication facilitation ?
Which of the following is not a conflict in software development team ?
Which of the following is not included in Issues Meetings ?
The CMM model is a technique to____________________?
Which of the following is needed by Maintenance staff?
A project usually has a timeline chart which was developed by_________________?