Which phase of the RUP is used to establish a business case for the system ?
Correct answer: D. Inception
- A. Transition
- B. Elaboration
- C. Construction
- D. Inception
Explanation
RUP's Inception phase establishes the system's scope, feasibility, objectives, and business case. Elaboration then concentrates on refining requirements and the architecture.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? [email protected]
Practise Software Development Lifecycle
423 free Software Development Lifecycle MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Software Engineering questions like this
Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.
More Software Development Lifecycle questions
Which one of the following is not a fundamental activity for software processes in software engineering ?
Selection of a model is based on_____________________?
Which of the following life cycle model can be chosen if the development team has less experience on similar projects ?
The RUP is normally described from three perspectives-dynamic, static & practice.What does static perspective do ?
How is Incremental Model different from Spiral Model ?
How is WINWIN Spiral Model different from Spiral Model ?