How is WINWIN Spiral Model different from Spiral Model ?
Correct answer: B. It defines a set of negotiation activities at the beginning of each pass around the spiral
- A. It defines tasks required to define resources, timelines, and other project related information
- B. It defines a set of negotiation activities at the beginning of each pass around the spiral
- C. It defines tasks required to assess both technical and management risks
- D. It defines tasks required to construct, test, install, and provide user support
Explanation
The WINWIN Spiral Model adds stakeholder negotiation at the start of every spiral cycle so that conflicting goals can be reconciled. The ordinary Spiral Model focuses on risk analysis without this formal negotiation activity.
Last updated
Practise Software Development Lifecycle
423 free Software Development Lifecycle MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Exams that ask Software Engineering questions like this
Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.
Related questions
Which of these is true ?
What is a Software ____________________ ?
Software engineers should not use their technical skills to misuse other people's computers."Here the term misuse refers to ___________________?
Explain what is meant by PRODUCT with reference to one of the eight principles as per the ACM/IEEE Code of Ethics ?
The reason for software bugs and failures is due to _____________________?