Which of the following is the essential requirement of peak load plant ?

Correct answer: D. It should be capable of starting quickly

  • A. It should run at high speed
  • B. It should produce high voltage
  • C. It should be small in size
  • D. It should be capable of starting quickly

Explanation

A peak-load plant operates for short periods and must respond rapidly when demand rises. Quick starting is therefore more essential than high speed, high voltage, or small size alone.

Written and checked by , MS Computer ScienceLast updated
Report an error

The more specific you are, the faster it gets fixed. A source beats an opinion.

Prefer email? [email protected]

Practise Power Systems

334 free Power Systems MCQs from Electrical Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.

Discussion

Stuck on an option, or know a faster way to get there? Ask or explain it here.

No comments yet. Be the first to explain this one.

Exams that ask Electrical Engineering questions like this

Electrical Engineering is on 2 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.

More Power Systems questions