Which of the following is not a main phase in Configuration Management (CM) Process ?
Correct answer: D. None of the mentioned
- A. CM Planning
- B. Executing the CM process
- C. CM audits
- D. None of the mentioned
Explanation
CM planning, execution, and CM audits are all recognised activities or phases of a configuration-management process. Therefore, none of the listed items is excluded.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? [email protected]
Practise Software Project Management
171 free Software Project Management MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Software Engineering questions like this
Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.
More Software Project Management questions
When code is made available to others, it goes in a/an____________________?
Which of the following is not a change management process ?
What allows different projects to use the same source files at the same time ?
SCM stands for_________________?
What is validating the completeness of a product ?
What is a collection of software elements treated as a unit for the purposes of SCM ?