Which of the following is not a change management process ?

Correct answer: D. None of the mentioned

  • A. Log the changes
  • B. Estimate impact on effort and schedule
  • C. Review impact with stakeholders
  • D. None of the mentioned

Explanation

Logging a requested change, estimating its effect on cost and schedule, and reviewing that effect with stakeholders are all normal change-management activities. Hence none of the listed actions is excluded.