Which of the following is not a change management process ?
Correct answer: D. None of the mentioned
- A. Log the changes
- B. Estimate impact on effort and schedule
- C. Review impact with stakeholders
- D. None of the mentioned
Explanation
Logging a requested change, estimating its effect on cost and schedule, and reviewing that effect with stakeholders are all normal change-management activities. Hence none of the listed actions is excluded.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? [email protected]
Practise Software Project Management
171 free Software Project Management MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Software Engineering questions like this
Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.
More Software Project Management questions
What allows different projects to use the same source files at the same time ?
Who has been sworn-in as the new chief justice of Allahabad High Court ?
The name 'Tim Cook' is associated with__________________?
When code is made available to others, it goes in a/an____________________?
Which of the following is not a main phase in Configuration Management (CM) Process ?
SCM stands for_________________?