What is validating the completeness of a product ?
Correct answer: C. Auditing and Reviewing
- A. Identification
- B. Software
- C. Auditing and Reviewing
- D. Status Accounting
Explanation
Auditing and reviewing checks whether a product is complete, consistent, and compliant with its requirements and configuration records. Identification labels items, while status accounting reports their current state.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? [email protected]
Practise Software Project Management
171 free Software Project Management MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Software Engineering questions like this
Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.
More Software Project Management questions
SCM stands for_________________?
Which of the following is not a main phase in Configuration Management (CM) Process ?
When code is made available to others, it goes in a/an____________________?
What is a collection of software elements treated as a unit for the purposes of SCM ?
What is one or more software configuration items that have been formally reviewed and agreed upon and serve as a basis for further development ?
What is group with the responsibility for reviewing and approving changes to baselines ?