Which of the following is a deliverable of the system implementation phase in a formal system development process ?

Correct answer: A. technical hardware and software solution for the business problem

  • A. technical hardware and software solution for the business problem
  • B. business problem statement
  • C. statement of the system users' business requirements
  • D. technical blueprint and specifications for a solution that fulfills the business requirements

Explanation

Implementation produces or installs the actual technical solution, including the required hardware and software. A business problem statement and user requirements belong to earlier analysis stages, while the technical blueprint is mainly a design-phase deliverable.

Written and checked by , MS Computer ScienceLast updated
Report an error

The more specific you are, the faster it gets fixed. A source beats an opinion.

Prefer email? [email protected]

Practise Software Development Lifecycle

423 free Software Development Lifecycle MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.

Discussion

Stuck on an option, or know a faster way to get there? Ask or explain it here.

No comments yet. Be the first to explain this one.

Exams that ask Software Engineering questions like this

Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.

More Software Development Lifecycle questions