The project planner examines the statement of scope and extracts all important software functions which is known as___________________?
Correct answer: B. Decomposition
- A. Association
- B. Decomposition
- C. Planning process
- D. All of the mentioned
Explanation
Decomposition breaks the project scope into smaller functions or work elements that can be estimated and planned. Association and planning process do not name this extraction technique.
Last updated
Practise Software Project Management
171 free Software Project Management MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Exams that ask Software Engineering questions like this
Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.
Related questions
Identify an ethical dilemma from the situations mentioned below ?
In terms of Issues related to professional responsibility____________________?
Select the incorrect statement: "Software engineers should:
Which of these are not among the eight principles followed by Software Engineering Code of Ethics and Professional Practice ?
As per an IBM report, "31%of the project get cancelled before they are completed, 53% overrun their cost estimates by an average of 189% and for every 100 projects, there are 94 restarts".What is the reason for these statistics ?