Quality planning is the process of developing a quality plan for__________________?
Correct answer: B. project
- A. team
- B. project
- C. customers
- D. project manager
Explanation
Quality planning defines the quality standards, procedures, responsibilities, and checks that will apply to a project. It is not a plan developed merely for an individual team member, customer, or manager.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? [email protected]
Practise Software Project Management
171 free Software Project Management MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Software Engineering questions like this
Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.
More Software Project Management questions
Which of the following is/are main parameters that you should use when computing the costs of a software development project ?
Which of the following is not considered as a risk in project management ?
The project planner examines the statement of scope and extracts all important software functions which is known as___________________?
The process each manager follows during the life of a project is known as ___________________?
Which of the following is incorrect activity for the configuration management of a software system ?
Which of the following is not project management goal ?