The process each manager follows during the life of a project is known as ___________________?
Correct answer: C. Project Management Life Cycle
- A. Project Management
- B. Manager life cycle
- C. Project Management Life Cycle
- D. All of the mentioned
Explanation
The project management life cycle describes the sequence of management activities from initiating and planning through execution, monitoring, and closure. “Manager life cycle” is not the standard term.
Last updated
Practise Software Project Management
171 free Software Project Management MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Exams that ask Software Engineering questions like this
Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.
Related questions
A graphical technique for finding if changes and variation in metrics data are meaningful is known as_________________?
A __________ is a measure, an intangible measure, which is difficult to count in clear terms?
A _______________ is developed using historical cost information that relates some software metric to the project cost ?
A listing of the names and addresses of all the employees for an organization would be an example of a(n)_________________________?
A make-buy decision is based on whether________________?