Cost and schedule are a part of_________________________?

Correct answer: C. Project Metrics

  • A. Product Metrics
  • B. Process Metrics
  • C. Project Metrics
  • D. All of the mentioned

Explanation

Cost and schedule measure how a project is progressing against its plan, so they are project metrics. Product metrics describe the software itself, while process metrics describe how development activities perform.