Which of the following is not an option to achieve reliable cost and effort estimate ?

Correct answer: D. The ability to translate the size estimate into human effort, calendar time, and dollars

  • A. Base estimates on similar projects that have already been completed
  • B. Use one or more empirical models for software cost and effort estimation
  • C. Use relatively simple decomposition techniques to generate project cost and effort estimates
  • D. The ability to translate the size estimate into human effort, calendar time, and dollars

Explanation

Reliable estimation can use completed similar projects, empirical models, or decomposition techniques. Translating size into effort, time, and money is the estimation outcome or capability, not a separate estimation option in this list.

Written and checked by , MS Computer ScienceLast updated
Report an error

The more specific you are, the faster it gets fixed. A source beats an opinion.

Prefer email? [email protected]

Practise Software Project Management

171 free Software Project Management MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.

Discussion

Stuck on an option, or know a faster way to get there? Ask or explain it here.

No comments yet. Be the first to explain this one.

Exams that ask Software Engineering questions like this

Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.

More Software Project Management questions