Generating capacity connected to the bus bars and ready to take load when switched on is known as____________?

Correct answer: D. spinning reserve

  • A. firm power
  • B. cold reserve
  • C. hot reserve
  • D. spinning reserve

Explanation

Spinning reserve is generating capacity already synchronized with and connected to the bus bars, so it can accept load immediately. Cold reserve units are shut down and require starting time before supplying power.