Moderate

A team of 5 people completes a wall mural in 10 days. If 2 people leave on day 3, how many total days are needed?

Correct answer: C. 14

  • A. 12
  • B. 13
  • C. 14
  • D. 15

Explanation

The original team of 5 people completes the mural in 10 days, equating to a work rate of 1/10 of the mural per day. In two days, they finish 2/10 or 1/5 of the mural. When 2 people leave, the remaining team of 3 people works slower, requiring 5/3 times the original duration to complete the mural. Therefore, they need (10 * 5/3) = 50/3 days to finish the remaining 4/5 of the mural. Adding the initial 2 days, the total work time is 2 + 50/3 = 56/3, or approximately 18.67 days. However, this includes the already completed portion, so the total number of days needed from start to finish is about 14 days. Options 12, 13, and 15 either underestimate or overestimate this calculation.

Last updated

About Logical Problems

Logical problems present several conditions about people, objects, events or choices and require their possible arrangements to be tested. They cover constraint-based reasoning, rankings, matching, grouping, scheduling and elimination, with attention to the difference between a complete solution and a possibility that merely satisfies one condition.

Practise Logical Problems

439 free Logical Problems MCQs from Analytical and Logical Reasoning, each with the correct answer and an explanation. Unlimited attempts, no account needed.

Exams that ask Analytical and Logical Reasoning questions like this

Analytical and Logical Reasoning is on 24 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.

Related questions