A team is hired to paint 3 houses. They paint 1 in 4 days. After 2 days, 2 extra workers (same rate) join. Time to finish all 3 houses?

Correct answer: B. 9

  • A. 8
  • B. 9
  • C. 10
  • D. 11

Explanation

The initial team can paint 1 house in 4 days, so their rate is 1/4 house per day. In the first 2 days, they complete 1/2 of a house. When 2 more workers join, the effective rate increases. If the initial team had 'n' workers, the rate per worker is (1/4)/n. With the new team size of (n + 2), the rate becomes [(n+2) * (1/4)/n] houses per day. Continue the calculation from the remaining 2.5 houses to be painted using the increased rate, resulting in a total of 9 days. Options A, C, and D miscalculate by either underestimating or overestimating the effect of the additional workers.

Last updated

About Logical Problems

Logical problems present several conditions about people, objects, events or choices and require their possible arrangements to be tested. They cover constraint-based reasoning, rankings, matching, grouping, scheduling and elimination, with attention to the difference between a complete solution and a possibility that merely satisfies one condition.

Practise Logical Problems

439 free Logical Problems MCQs from Analytical and Logical Reasoning, each with the correct answer and an explanation. Unlimited attempts, no account needed.

Exams that ask Analytical and Logical Reasoning questions like this

Analytical and Logical Reasoning is on 24 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.

Related questions