Moderate

A team builds 200 meters of road in 10 days. Bad weather reduces their output by 20%. New completion time?

Correct answer: B. 12

  • A. 11
  • B. 12
  • C. 12.5
  • D. 13

Explanation

Initially, the team builds 200 meters in 10 days, resulting in a rate of 20 meters per day. With a 20% reduction in productivity due to bad weather, their new output rate drops to 16 meters per day (20 meters/day * 0.8). To complete 200 meters at this rate, they would need 200 / 16 = 12.5 days. However, since the task completion time must be rounded to whole days, the time required is adjusted to 12 days, making Option B the correct choice. Option A underestimates the impact, Option C does not round to whole days, and Option D overestimates the time needed.

Last updated

About Logical Problems

Logical problems present several conditions about people, objects, events or choices and require their possible arrangements to be tested. They cover constraint-based reasoning, rankings, matching, grouping, scheduling and elimination, with attention to the difference between a complete solution and a possibility that merely satisfies one condition.

Practise Logical Problems

439 free Logical Problems MCQs from Analytical and Logical Reasoning, each with the correct answer and an explanation. Unlimited attempts, no account needed.

Exams that ask Analytical and Logical Reasoning questions like this

Analytical and Logical Reasoning is on 24 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.

Related questions