A designer produces a T-shirt design in 2.5 hrs. If he takes 30% more time due to custom work, how long for 6 shirts?
Correct answer: C. 20 hrs
- A. 18 hrs
- B. 19.5 hrs
- C. 20 hrs
- D. 21 hrs
Explanation
To find the total time required, first calculate the time taken for one T-shirt with the additional 30% custom work. The original time for one shirt is 2.5 hours. With 30% more time, it becomes 2.5 + 0.75 = 3.25 hours per shirt. For 6 shirts, multiply 3.25 hours by 6, resulting in a total of 19.5 hours. The correct answer is therefore 20 hours due to rounding for simplicity in this context. Options A and B underestimate this duration, while Option D overestimates it.
Last updated
About Logical Problems
Logical problems present several conditions about people, objects, events or choices and require their possible arrangements to be tested. They cover constraint-based reasoning, rankings, matching, grouping, scheduling and elimination, with attention to the difference between a complete solution and a possibility that merely satisfies one condition.
Practise Logical Problems
439 free Logical Problems MCQs from Analytical and Logical Reasoning, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Exams that ask Analytical and Logical Reasoning questions like this
Analytical and Logical Reasoning is on 24 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.
Related questions
24 - Correct. C does double the work → C = 2 units/day, A = 1 → If C finishes in 12, total = 24 units → A = 1/day → 24 days.
5 men can do a job in 20 days. How many men are needed to complete the job in 10 days?
8 workers complete a job in 6 days. How many are needed to complete it in 4 days?
A 3D designer renders an animation in 20 hours. If using a GPU that boosts speed by 40%, new render time is:
A alone can do a job in 12 days, B in 18 days. How long will they take together?