A coding team of 4 people completes a software module in 12 days. After 4 days, one coder leaves. How many days will the rest take to complete it?
Correct answer: C. 11
- A. 9
- B. 10
- C. 11
- D. 12
Explanation
Initially, the team of 4 coders has a work rate of 1 module per 12 days, which means the team's combined work rate is 1/12 of a module per day. In 4 days, they complete 4/12 = 1/3 of the module, leaving 2/3 of the work remaining.After one coder leaves, only 3 coders remain. Their new work rate is 3/4 of the original work rate, or (3/4) * (1/12) = 1/16 of a module per day. To complete the remaining 2/3 of the module, they need (2/3) / (1/16) = 32/3 days, which is approximately 10.67 days. Since they cannot work a fraction of a day, it rounds up to 11 days.Thus, the remaining 3 coders will take 11 more days to finish the module. The other options are incorrect because they do not account for the accurate reduction in work rate and the amount of work already completed.
Last updated
About Logical Problems
Logical problems present several conditions about people, objects, events or choices and require their possible arrangements to be tested. They cover constraint-based reasoning, rankings, matching, grouping, scheduling and elimination, with attention to the difference between a complete solution and a possibility that merely satisfies one condition.
Practise Logical Problems
439 free Logical Problems MCQs from Analytical and Logical Reasoning, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Exams that ask Analytical and Logical Reasoning questions like this
Analytical and Logical Reasoning is on 24 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.
Related questions
24 - Correct. C does double the work → C = 2 units/day, A = 1 → If C finishes in 12, total = 24 units → A = 1/day → 24 days.
5 men can do a job in 20 days. How many men are needed to complete the job in 10 days?
8 workers complete a job in 6 days. How many are needed to complete it in 4 days?
A 3D designer renders an animation in 20 hours. If using a GPU that boosts speed by 40%, new render time is:
A alone can do a job in 12 days, B in 18 days. How long will they take together?