  • A. maximum capital budget
  • B. greater capital budget
  • C. optimal capital budget
  • D. minimum capital budget

Explanation: When a firm approaches its optimal capital budget, the marginal cost of capital may increase and available funds may become subject to…

Correct answer: optimal capital budget
  • A. net present value method
  • B. net future value method
  • C. net capital budgeting method
  • D. net equity budgeting method

Explanation: The net present value method is a discounted-cash-flow technique because it discounts expected future cash flows back to their present…

Correct answer: net present value method
  • A. terminal value
  • B. existed value
  • C. quit value
  • D. relative value

Explanation: The compounded value of a project's cash flows at the end of its life is called its terminal value.

Correct answer: terminal value
  • A. negative numbers
  • B. positive numbers
  • C. hurdle number
  • D. relative number

Explanation: Project costs are cash outflows and are recorded as negative numbers in capital-budgeting analysis.

Correct answer: negative numbers
  • A. minimum life
  • B. present value life
  • C. economic life
  • D. transaction life

Explanation: Economic life is the period over which an asset provides the most economically beneficial service, commonly the life that maximizes its…

Correct answer: economic life
  • A. technical equity
  • B. defined future value
  • C. project net present value
  • D. equity net present value

Explanation: Net present value is obtained by adding the present values of all project cash flows, including the initial investment as a negative…

Correct answer: project net present value
  • A. present value consent
  • B. mutually exclusive
  • C. mutual project
  • D. mutual consent

Explanation: Mutually exclusive projects cannot both be selected, so accepting one requires rejecting the other.

Correct answer: mutually exclusive
  • A. present value of equity
  • B. future value of equity
  • C. present value cash flow
  • D. future value of cash flow

Explanation: NPV calculation begins by discounting each future cash flow to its present value, after which the initial investment and discounted…

Correct answer: present value cash flow
  • A. non-normal cash flow
  • B. normal cash flow
  • C. normal costs
  • D. non-normal costs

Explanation: A non-normal cash flow changes sign more than once, such as moving from negative to positive and later back to negative.

Correct answer: non-normal cash flow
  • A. greater than two
  • B. equal to
  • C. less than one
  • D. greater than one

Explanation: Profitability index equals the present value of future inflows divided by the initial investment.

Correct answer: greater than one
  • A. negative index
  • B. exchange index
  • C. project index
  • D. profitability index

Explanation: The ratio of the present value of future cash flows to the project's initial cost is called the profitability index.

Correct answer: profitability index
  • A. 8200
  • B. 16000
  • C. 0.0064
  • D. 1562.5

Explanation: Profitability index equals the present value of future cash flows divided by the initial investment. Therefore, PV = 3.2 × $5,000 = $16,000.

Correct answer: 16000
  • A. optimal rationing
  • B. capital rationing
  • C. marginal rationing
  • D. transaction rationing

Explanation: Capital rationing occurs when a firm places a limit on the funds available for capital investment.

Correct answer: capital rationing
  • A. one
  • B. multiple
  • C. accepted
  • D. non-accepted

Explanation: Non-normal cash flows involve more than one change between outflows and inflows, so they may produce multiple internal rates of return.

Correct answer: multiple
  • A. be reinvested
  • B. not be reinvested
  • C. be earned
  • D. not be earned

Explanation: The traditional IRR method assumes that interim cash inflows can be reinvested at the project’s IRR.

Correct answer: be reinvested
  • A. less project return
  • B. greater project return
  • C. shorter payback period
  • D. greater payback period

Explanation: A shorter payback period means the investment is recovered sooner, increasing project liquidity and reducing the time funds remain tied…

Correct answer: shorter payback period
  • A. negative projects
  • B. relative projects
  • C. evaluate projects
  • D. earned projects

Explanation: The profitability index evaluates the value created per unit of investment and is particularly useful for comparing or ranking projects…

Correct answer: evaluate projects
  • A. 0.55
  • B. 1.82
  • C. 0.55
  • D. 0.0182

Explanation: Profitability index = present value of future cash flows ÷ initial cost = $2,000 ÷ $1,100 = 1.82 approximately.

Correct answer: 1.82
  • A. negative
  • B. zero
  • C. positive
  • D. independent

Explanation: When a project’s discounted cash flows exactly recover the investment at the required rate of return, its net present value is zero.

Correct answer: zero
  • A. 3.46 years
  • B. 2.46 years
  • C. 5.46 years
  • D. 4.46 years

Explanation: Payback period = completed years + unrecovered cost ÷ recovery-year cash flow = 4 + $300 ÷ $650 = 4.46 years.

Correct answer: 4.46 years