All Free Civil Engineering MCQs with Answers

Every Civil Engineering question in the bank, across all chapters, each with the correct answer and a written explanation. Free and unlimited, with no account needed.

631 questions · page 29 of 32

  • A. Stopping sight distance
  • B. Intersection sight distance
  • C. Headlight sight distance
  • D. Decision sight distance

Explanation: Intersection sight distance allows a driver to see enough of the major road to accept a gap and complete the intended manoeuvre safely.

Correct answer: Intersection sight distance
  • A. Pavement colour and aggregate shape
  • B. Traffic signal timing and lane markings
  • C. Horizontal curves, sight distance and superelevation
  • D. Bridge bearings and drainage outlet size

Explanation: Design speed provides the basis for selecting geometric elements such as curve radius, sight distance and superelevation.

Correct answer: Horizontal curves, sight distance and superelevation
  • A. 500 vehicles per hour
  • B. 1,000 vehicles per hour
  • C. 2,400 vehicles per hour
  • D. 1,800 vehicles per hour

Explanation: Traffic flow equals density multiplied by average speed, so q = 30 × 60 = 1,800 vehicles per hour.

Correct answer: 1,800 vehicles per hour
  • A. Express mixed traffic as an equivalent passenger-car flow
  • B. Estimate pavement layer thickness directly
  • C. Determine the legal speed limit on a road
  • D. Calculate the axle load of a heavy vehicle

Explanation: Passenger car units provide a common measure for traffic streams containing cars, buses, trucks and other vehicles.

Correct answer: Express mixed traffic as an equivalent passenger-car flow
  • A. A uniform pavement colour
  • B. A high proportion of slow heavy vehicles
  • C. A wider road shoulder beyond the carriageway
  • D. A lower number of roadside advertisements

Explanation: Slow heavy vehicles occupy road space and reduce passing opportunities, especially on two-lane roads.

Correct answer: A high proportion of slow heavy vehicles
  • A. The intersection is closed to all traffic
  • B. The pedestrian phase has permanently ended
  • C. The signal is changing from green to red
  • D. The road is changing from two-way to one-way operation

Explanation: The yellow interval provides a transition between the green and red indications and warns approaching drivers to stop if it is safe to do…

Correct answer: The signal is changing from green to red
  • A. A fog spray
  • B. A prime coat
  • C. A seal coat
  • D. A tack coat

Explanation: A tack coat is a light application of bituminous material used to bond successive bituminous layers.

Correct answer: A tack coat
  • A. Transfer wheel loads across the joint
  • B. Increase surface friction during rain
  • C. Prevent all thermal expansion of concrete
  • D. Replace the need for longitudinal drainage

Explanation: Dowel bars transfer load from one slab to the adjoining slab while permitting the joint to open and close.

Correct answer: Transfer wheel loads across the joint
  • A. Upward movement of bitumen through asphalt pores
  • B. Ejection of water and soil through joints under wheel loads
  • C. Expansion of concrete caused by high temperature
  • D. Loss of aggregate caused by wind erosion

Explanation: Pumping occurs when repeated wheel loads force water and fine subgrade material through joints or cracks.

Correct answer: Ejection of water and soil through joints under wheel loads
  • A. Fish plate
  • B. Check rail
  • C. Sleeper
  • D. Rail flange

Explanation: Sleepers maintain the rail spacing and transmit rail loads to the ballast or supporting formation.

Correct answer: Sleeper
  • A. Steel rail before fixing it to sleepers
  • B. Finished asphalt surface to restore skid resistance
  • C. Concrete joint to transfer wheel loads
  • D. Clean granular base before placing a bituminous layer

Explanation: A prime coat penetrates and binds the surface of an absorbent granular base before the bituminous pavement layer is placed.

Correct answer: Clean granular base before placing a bituminous layer
  • A. Overtake safely without conflicting with opposing traffic
  • B. Stop before reaching a roadside hazard
  • C. Enter a highway from an adjoining property
  • D. Pass through a signalized intersection safely

Explanation: Overtaking sight distance allows a vehicle to pass a slower vehicle and return to its lane without interfering with an approaching…

Correct answer: Overtake safely without conflicting with opposing traffic
  • A. Steepest gradient permitted for emergency use
  • B. Maximum desirable gradient under normal conditions
  • C. Average gradient measured along the entire route
  • D. Gradient provided only at a horizontal curve

Explanation: The ruling gradient is the maximum desirable slope used in ordinary highway design, considering vehicle performance and operating…

Correct answer: Maximum desirable gradient under normal conditions
  • A. Design speed
  • B. Free-flow speed
  • C. Critical speed
  • D. Spot speed

Explanation: Flow equals speed multiplied by density, and its maximum value occurs at the critical speed.

Correct answer: Critical speed
  • A. Seal an unpaved subgrade before base placement
  • B. Reduce evaporation from fresh concrete
  • C. Improve the bearing capacity of weak soil
  • D. Bond an existing bituminous surface to a new layer

Explanation: A tack coat is a thin bituminous application used to bond two bituminous layers.

Correct answer: Bond an existing bituminous surface to a new layer
  • A. Permanent deformation under applied load
  • B. Water absorption by the aggregate
  • C. Abrasion of railway ballast particles
  • D. Shrinkage cracking in cement concrete

Explanation: Marshall stability is the maximum load carried by a compacted bituminous specimen at the specified test temperature and loading rate.

Correct answer: Permanent deformation under applied load
  • A. The chemical reaction between bitumen and aggregate
  • B. A difference in temperature between the top and bottom surfaces
  • C. The impact of vehicles at expansion joints
  • D. The unequal spacing of railway sleepers

Explanation: Temperature differences through the slab depth cause the concrete pavement to curl or warp, producing warping stresses.

Correct answer: A difference in temperature between the top and bottom surfaces
  • A. Join two rail ends with a fishplate
  • B. Provide electrical power to signalling equipment
  • C. Distribute sleeper loads and provide drainage
  • D. Maintain the exact length of each rail

Explanation: Ballast distributes loads from sleepers to the formation, provides drainage, and helps maintain track alignment.

Correct answer: Distribute sleeper loads and provide drainage
  • A. Passenger lounge and baggage hall
  • B. Control tower and weather station
  • C. Fuel farm and airport boundary
  • D. Runway and apron or terminal area

Explanation: Taxiways allow aircraft to move between runways and operational areas such as aprons, hangars, and terminals.

Correct answer: Runway and apron or terminal area
  • A. Stripping caused by loss of adhesion from water
  • B. Ravelling caused only by surface oxidation
  • C. Bleeding caused only by excessive road camber
  • D. Corrugation caused only by rail traffic

Explanation: Water can destroy the bond between bitumen and aggregate, producing stripping and weakening the pavement structure.

Correct answer: Stripping caused by loss of adhesion from water