Who controls the FAST (Facilitated Application Specification Techniques) meeting ?
Correct answer: C. Facilitator
- A. System Analyst
- B. Scribe
- C. Facilitator
- D. Manager
Explanation
The facilitator manages the FAST meeting by guiding discussion, keeping participants focused, and resolving procedural issues. The scribe records decisions, while the system analyst contributes requirements expertise rather than controlling the session.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? [email protected]
Practise Requirements Engineering
125 free Requirements Engineering MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Software Engineering questions like this
Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.
More Requirements Engineering questions
Choose the incorrect statement with respect to Non-Functional Requirement(NFR) ?
According to components of FURPS+, which of the following does not belong to S ?
Choose the correct statement on how NFRs integrates with Rational Unified Process ?
Choose the disadvantage of using SSM as an elicitation technique ?
Which of the following Requirement Elicitation Techniques is applicable to messy, changing and ill-defined problem situations ?
Keeping the requirements of QFD in mind which of the following is not an example of an Expected Requirement ?