Which of the following phases is unique to the commercial application package implementation strategy as opposed to the rapid application development strategy ?
Correct answer: D. business process design
- A. problem analysis
- B. construction and testing
- C. scope definition
- D. business process design
Explanation
Commercial package implementation requires business process design to adapt organizational procedures to the selected package. Scope definition, analysis, and construction or testing are also common in rapid application development.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? [email protected]
Practise Software Development Lifecycle
423 free Software Development Lifecycle MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Software Engineering questions like this
Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.
More Software Development Lifecycle questions
Which of the following is an advantage of discovery prototyping ?
Remote batch processing has the following characteristic(s)_______________?
The flow of information through MIS is_________________?
Which of the following is(are) the step(s) in the output design process ?
A cross life-cycle activity of system development is____________________?
A task of developing a technical blueprint and specifications for a solution that fulfills the business requirements is undertaken in the following phase of the system development process ?