Which of the following is not a project factor that should be considered when planning the structure of software engineering teams ?

Correct answer: C. The degree of sociability required for the project

  • A. The difficulty of the problem to be solved
  • B. High frustration caused by personal, business, or technological factors that causes friction among team members
  • C. The degree of sociability required for the project
  • D. The rigidity of the delivery date

Explanation

The degree of sociability required is not a standard project factor used to plan software team structure. Problem difficulty, interpersonal friction, and delivery-date rigidity can directly influence the appropriate team organization.

Written and checked by , MS Computer ScienceLast updated
Report an error

The more specific you are, the faster it gets fixed. A source beats an opinion.

Prefer email? [email protected]

Practise Software Project Management

171 free Software Project Management MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.

Discussion

Stuck on an option, or know a faster way to get there? Ask or explain it here.

No comments yet. Be the first to explain this one.

Exams that ask Software Engineering questions like this

Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.

More Software Project Management questions