Which of the following is an activity that distributes estimated effort across the planned project duration by allocating the effort to specific software engineering tasks ?
Correct answer: B. Software Project scheduling
- A. Software Macroscopic schedule
- B. Software Project scheduling
- C. Software Detailed schedule
- D. None of the mentioned
Explanation
Software project scheduling distributes the estimated effort over the project duration and assigns it to specific engineering tasks. A macroscopic schedule is higher-level, while a detailed schedule is a possible output or refinement rather than the named activity.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? [email protected]
Practise Software Project Management
171 free Software Project Management MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Software Engineering questions like this
Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.
More Software Project Management questions
SPMP stands for__________________?
Which software engineering team has no permanent leader ?
Which of the following is a people-intensive activity ?
Which of the following is not a project factor that should be considered when planning the structure of software engineering teams ?
Which type of software engineering team has a defined leader who coordinates specific tasks and secondary leaders that have responsibility for sub tasks ?
Who interacts with the software once it is released for production use ?