Moderate

Which of the following is included in SRS ?

Correct answer: B. Design Constraints

  • A. Cost
  • B. Design Constraints
  • C. Staffing
  • D. Delivery Schedule

Explanation

Design constraints belong in an SRS because they restrict the acceptable implementation, such as required technologies, standards, interfaces, or hardware. Cost, staffing, and delivery scheduling are project-management concerns rather than product requirements.