When high flood passing down weir creating high up lift pressures and there is no flow in the canals, if such condition is taken for design and is called__________________?

Correct answer: D. Worst condition

  • A. High flood level
  • B. Dangerous condition
  • C. Hydraulic design condition
  • D. Worst condition

Explanation

The combination of high flood discharge over the weir and no canal flow produces maximum uplift and is treated as the worst condition for design. It is a critical loading case rather than merely the high flood level.

Written and checked by , editorLast updated
Report an error

The more specific you are, the faster it gets fixed. A source beats an opinion.

Prefer email? [email protected]

Practise Irrigation and Water Management

262 free Irrigation and Water Management MCQs from Agriculture, each with the correct answer and an explanation. Unlimited attempts, no account needed.

Discussion

Stuck on an option, or know a faster way to get there? Ask or explain it here.

No comments yet. Be the first to explain this one.

Exams that ask Agriculture questions like this

Agriculture is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.

More Irrigation and Water Management questions