Moderate

When high flood passing down weir creating high up lift pressures and there is no flow in the canals, if such condition is taken for design and is called__________________?

Correct answer: D. Worst condition

  • A. High flood level
  • B. Dangerous condition
  • C. Hydraulic design condition
  • D. Worst condition

Explanation

The combination of high flood discharge over the weir and no canal flow produces maximum uplift and is treated as the worst condition for design. It is a critical loading case rather than merely the high flood level.