What is the main purpose of a construction method statement?
Correct answer: B. To describe how a particular work activity will be carried out
- A. To certify the final value of completed work
- B. To describe how a particular work activity will be carried out
- C. To replace the contract drawings after award
- D. To record payments made to subcontractors
Explanation
A method statement sets out the planned sequence, resources, controls, and sometimes hazards for carrying out a specific activity. It does not replace design documents or serve as a payment certificate.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? [email protected]
About Construction Management and Estimation
Construction management covers planning, scheduling, resource control, contracts, procurement, site organisation, safety, quality assurance and project documentation. Estimation includes quantity take-off, rate analysis, bill preparation, valuation and cost control, with attention to the difference between direct and indirect costs and between an estimate, a tender and a final account.
Practise Construction Management and Estimation
80 free Construction Management and Estimation MCQs from Civil Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Civil Engineering questions like this
Civil Engineering is on 3 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.
More Construction Management and Estimation questions
What does an abstract of cost in a construction estimate normally present?
A revised estimate for a public works project is generally prepared when:
Which scheduling technique uses probabilistic activity durations to estimate the likely completion time of a construction project?
The slump test for fresh concrete primarily indicates its:
In construction documentation, a punch list is mainly used to record:
What is the usual purpose of a mobilisation advance paid under a construction contract?