In construction documentation, a punch list is mainly used to record:

Correct answer: D. Outstanding defects or incomplete work before handover

  • A. The sequence of activities in the baseline programme
  • B. The original quantities used for tender pricing
  • C. The approved list of project suppliers
  • D. Outstanding defects or incomplete work before handover

Explanation

A punch list identifies minor defects, omissions, and unfinished items that must be corrected before completion or handover. It is not a tender document or a replacement for the project schedule.

Written and checked by , MS Computer ScienceLast updated
Report an error

The more specific you are, the faster it gets fixed. A source beats an opinion.

Prefer email? support@testustad.com

About Construction Management and Estimation

Construction management covers planning, scheduling, resource control, contracts, procurement, site organisation, safety, quality assurance and project documentation. Estimation includes quantity take-off, rate analysis, bill preparation, valuation and cost control, with attention to the difference between direct and indirect costs and between an estimate, a tender and a final account.

Practise Construction Management and Estimation

80 free Construction Management and Estimation MCQs from Civil Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.

Discussion

Stuck on an option, or know a faster way to get there? Ask or explain it here.

No comments yet. Be the first to explain this one.

Exams that ask Civil Engineering questions like this

Civil Engineering is on 3 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.

More Construction Management and Estimation questions