In construction documentation, a punch list is mainly used to record:
Correct answer: D. Outstanding defects or incomplete work before handover
- A. The sequence of activities in the baseline programme
- B. The original quantities used for tender pricing
- C. The approved list of project suppliers
- D. Outstanding defects or incomplete work before handover
Explanation
A punch list identifies minor defects, omissions, and unfinished items that must be corrected before completion or handover. It is not a tender document or a replacement for the project schedule.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? support@testustad.com
About Construction Management and Estimation
Construction management covers planning, scheduling, resource control, contracts, procurement, site organisation, safety, quality assurance and project documentation. Estimation includes quantity take-off, rate analysis, bill preparation, valuation and cost control, with attention to the difference between direct and indirect costs and between an estimate, a tender and a final account.
Practise Construction Management and Estimation
80 free Construction Management and Estimation MCQs from Civil Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Civil Engineering questions like this
Civil Engineering is on 3 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.
More Construction Management and Estimation questions
The slump test for fresh concrete primarily indicates its:
What is the main purpose of a construction method statement?
What does an abstract of cost in a construction estimate normally present?
What is the usual purpose of a mobilisation advance paid under a construction contract?
A force majeure provision in a construction contract mainly deals with:
In traditional design-bid-build procurement, which party normally completes the design before construction tendering?