_____________ type of budgeting is based on estimation of total project cost by the top management?

Correct answer: A. Top down

  • A. Top down
  • B. Bottom up
  • C. Neutral
  • D. Zero-based

Explanation

Top-down budgeting begins with senior management estimating the overall project cost and then allocating amounts to lower levels. Bottom-up budgeting instead builds the total from detailed estimates made by teams or activities.