_____________ type of budgeting is based on estimation of total project cost by the top management?
Correct answer: A. Top down
- A. Top down
- B. Bottom up
- C. Neutral
- D. Zero-based
Explanation
Top-down budgeting begins with senior management estimating the overall project cost and then allocating amounts to lower levels. Bottom-up budgeting instead builds the total from detailed estimates made by teams or activities.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? [email protected]
Practise Software Project Management
171 free Software Project Management MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Software Engineering questions like this
Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.
More Software Project Management questions
Which level of an organization is responsible for setting medium term goals and allocating resources ?
Deciding how to carry out specific tasks by strategic and middle management and establishing criteria for completion and resource allocation best describes ?
Management, science, also known as ___________ , is a field of applied mathematics ?
Project Management ensures that______________?
Decision making process has been proposed by _______ in _______?
A ___________________ strategy seeks to achieve competitive advantages by allowing the business unit to make more profit than its competitors?