_____________ type of budgeting is based on estimation of total project cost by the top management?

Correct answer: A. Top down

  • A. Top down
  • B. Bottom up
  • C. Neutral
  • D. Zero-based

Explanation

Top-down budgeting begins with senior management estimating the overall project cost and then allocating amounts to lower levels. Bottom-up budgeting instead builds the total from detailed estimates made by teams or activities.

Written and checked by , MS Computer ScienceLast updated
Report an error

The more specific you are, the faster it gets fixed. A source beats an opinion.

Prefer email? [email protected]

Practise Software Project Management

171 free Software Project Management MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.

Discussion

Stuck on an option, or know a faster way to get there? Ask or explain it here.

No comments yet. Be the first to explain this one.

Exams that ask Software Engineering questions like this

Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.

More Software Project Management questions