Total product cost of a chemical plant does not include the ______________ cost?
Correct answer: A. Market survey
- A. Market survey
- B. Operating labour, supervision and supplies
- C. Overhead and utilities
- D. Depreciation, property tax and insurance
Explanation
Total product cost covers manufacturing expenses such as labour, utilities, supplies, overhead, depreciation, taxes, and insurance. Market survey is a preproduction or project-development expense, not a product cost.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? support@testustad.com
Practise Plant Design and Economics
803 free Plant Design and Economics MCQs from Chemical Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Exams that ask Chemical Engineering questions like this
Chemical Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.
More Plant Design and Economics questions
Personnel working in the market research group is responsible for the job of__________________?
Which of the following is not a component of working capital ?
In an ordinary chemical plant, electrical installation cost may be about ____________________?
If 'S' is the amount available after 'n' interest periods for an initial principal 'P' with the discrete compound interest rate 'i', the present worth is given by__________________?
Which of the following is not a component of the fixed capital for a chemical plant facility ?
Annual depreciation costs are constant, when the ______________ method of depreciation calculation is used ?