Moderate

The process of requirements discovery consists of the following activities, except_______________?

Correct answer: B. sampling of existing documentation, forms and files

  • A. requirements management
  • B. sampling of existing documentation, forms and files
  • C. requirements discovery
  • D. problem discovery and analysis

Explanation

Sampling existing documents, forms, and files is a technique used during requirements investigation, not one of the main activities in the requirements discovery process. Requirements management, problem analysis, and discovery are recognized process activities.

Last updated

Practise Requirements Engineering

125 free Requirements Engineering MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.

Exams that ask Software Engineering questions like this

Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.