The operating velocity in the absorption tower is usually 40-50% of the flooding velocity. Packed absorption towers are normally designed for a pressure drop of about _________________ mm of water column per metre height of packing?

Correct answer: B. 20-40

  • A. 1-5
  • B. 20-40
  • C. 100-150
  • D. 1000-1500

Explanation

Packed absorption towers commonly operate at about 40–50% of flooding velocity and are designed for roughly 20–40 mm water column pressure drop per metre of packing. The smaller range is generally too low for practical packing operation.

Written and checked by , MS Computer ScienceLast updated
Report an error

The more specific you are, the faster it gets fixed. A source beats an opinion.

Prefer email? support@testustad.com

Practise Mass Transfer Operations

669 free Mass Transfer Operations MCQs from Chemical Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.

Exams that ask Chemical Engineering questions like this

Chemical Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.

More Mass Transfer Operations questions