Moderate

The first CMM level at which measurable goals for quality and productivity are established is______________?

Correct answer: D. Level 4

  • A. Level 1
  • B. Level 2
  • C. Level 3
  • D. Level 4

Explanation

CMM Level 4, the Managed level, introduces quantitative and measurable goals for process quality and productivity. Earlier levels focus on basic, repeatable, or defined processes without this degree of measurement.