Moderate
The efficiency of a plant is of least concern when it is selected as___________?
Correct answer: C. either A. or (b)
- A. peak load plant
- B. casual run plant
- C. either A. or (b)
- D. base load plant
Explanation
Efficiency matters least for a peak-load or casual-run plant because it operates for relatively few hours. High efficiency is especially important for base-load plants that run continuously, so either option A or B fits.
Last updated
Practise Power Systems
334 free Power Systems MCQs from Electrical Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Exams that ask Electrical Engineering questions like this
Electrical Engineering is on 2 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.