The efficiency of a plant is of least concern when it is selected as___________?

Correct answer: C. either A. or (b)

  • A. peak load plant
  • B. casual run plant
  • C. either A. or (b)
  • D. base load plant

Explanation

Efficiency matters least for a peak-load or casual-run plant because it operates for relatively few hours. High efficiency is especially important for base-load plants that run continuously, so either option A or B fits.