Pakistan has signed an agreement with China for _______MW Azad Pattan hydropower Project in July 2020?
Correct answer: D. 700
- A. 800
- B. 300
- C. 100
- D. 700
Explanation
The Azad Pattan Hydropower Project was agreed with China as a 700-megawatt project under the China-Pakistan economic cooperation framework. The lower figures in the options refer to neither the project's planned capacity nor its commonly reported specification.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? support@testustad.com
About CPEC and Development Projects
The China-Pakistan Economic Corridor covers its routes, Gwadar Port, energy projects, transport links, industrial zones, digital connectivity and cooperation under its long-term development framework. The topic also includes major dams, highways, airports, power plants and other national projects, distinguishing CPEC initiatives from Pakistan’s broader public development programme.
Practise CPEC and Development Projects
283 free CPEC and Development Projects MCQs from Pakistan Current Affairs, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Pakistan Current Affairs questions like this
Pakistan Current Affairs is on 76 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.
More CPEC and Development Projects questions
On Aug 07,2020 PM Imran Khan launched the Ravi Urban Development Project under which Ravi City would be created north of lahore near the Ravi river at a cost of_________?
PM Imran Khan Inaugurated Peshawar BRT on__________August, 2020?
BRT stands for:_____________?
Pakistan has found new deposits of oil and gas in exploratory well Mamikhel South-01, located in Tal block in__________?
Pakistan has achieved the UN Sustainable Development Goal for protecting the environment and holding off climate change a ________ years before the deadline?
Pakistan aims to generate 30% of clean energy by_________?