Most of the high transmission lines in Pakistan are_______________?

Correct answer: B. overhead

  • A. underground
  • B. overhead
  • C. either of the above
  • D. none of the above

Explanation

Most high-voltage transmission lines in Pakistan are overhead because overhead construction is much cheaper and easier to inspect and repair than underground construction. Underground lines are used mainly where space or appearance is critical.