In sensitivity analysis, what does the allowable increase of an objective coefficient indicate?
Correct answer: C. The increase possible without changing the current optimal basis
- A. The increase in total available resources
- B. The increase possible before feasibility is lost
- C. The increase possible without changing the current optimal basis
- D. The increase in the number of decision variables
Explanation
The allowable increase shows how much an objective coefficient can rise while the current optimal basis remains optimal. It does not directly measure a change in resource availability or the feasible region.
Report an error
The more specific you are, the faster it gets fixed. A source beats an opinion.
Prefer email? [email protected]
About Linear Programming
Linear programming models the maximum or minimum of an objective function subject to linear constraints. Questions involve translating word conditions into inequalities, drawing the feasible region, identifying corner points and evaluating the objective function, including cases involving non-negativity restrictions and redundant constraints.
Practise Linear Programming
30 free Linear Programming MCQs from Quantitative Methods, each with the correct answer and an explanation. Unlimited attempts, no account needed.
Discussion
Stuck on an option, or know a faster way to get there? Ask or explain it here.
No comments yet. Be the first to explain this one.
Exams that ask Quantitative Methods questions like this
Quantitative Methods is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.
More Linear Programming questions
If a primal maximization problem and its dual minimization problem are both feasible, which relationship must hold for any feasible pair of solutions?
Which statement best distinguishes a feasible solution from a basic feasible solution?
In the simplex method for a maximization problem, which variable usually enters the basis?
A company produces products A and B. Product A earns Rs. 30 and uses 2 labour hours, while product B earns Rs. 20 and uses 1 labour hour. If at most 100 labour hours are available, which objective function represents profit maximization?
Maximize Z = 5x + 4y subject to 2x + y ≤ 8, x + 2y ≤ 8, and x, y ≥ 0. What is the optimal value of Z?
What is a redundant constraint in a linear programming model?