Moderate

In a single bus-bar system there will be complete shut down when____________?

Correct answer: A. fault occurs on the bus itself

  • A. fault occurs on the bus itself
  • B. fault occurs on neutral line
  • C. two or more faults occur simultaneously
  • D. fault occurs with respect to earthing

Explanation

In a single-bus arrangement, every circuit is connected to the same bus, so a bus fault can disconnect or shut down all connected circuits. A fault on one feeder does not normally require a complete bus shutdown.

Last updated

Practise Power Systems

334 free Power Systems MCQs from Electrical Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.

Exams that ask Electrical Engineering questions like this

Electrical Engineering is on 2 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.