Moderate

A team of 4 construction workers can build a small bridge in 10 days. If they hire 2 more workers after 4 days, total time is

Correct answer: A. 8 days

  • A. 8 days
  • B. 9 days
  • C. 9.5 days
  • D. 10 days

Explanation

The team of 4 workers can finish the bridge in 10 days, so their daily work rate is 1/10. After 4 days, they complete 4/10 or 40% of the work. To finish the remaining 60%, they hire 2 more workers, making a team of 6. The new work rate is 6/10 per day. Consequently, they complete the remaining 60% in 4 days. Hence, the total time taken is 4 days (initial) + 4 days (with additional workers) = 8 days.Option B (9 days) miscalculates the time needed after hiring, not fully accounting for the increased work rate. Option C (9.5 days) misapplies the new work rate, leading to an overestimation. Option D (10 days) ignores the addition of more workers and their impact on the work rate.

Last updated

About Logical Problems

Logical problems present several conditions about people, objects, events or choices and require their possible arrangements to be tested. They cover constraint-based reasoning, rankings, matching, grouping, scheduling and elimination, with attention to the difference between a complete solution and a possibility that merely satisfies one condition.

Practise Logical Problems

439 free Logical Problems MCQs from Analytical and Logical Reasoning, each with the correct answer and an explanation. Unlimited attempts, no account needed.

Exams that ask Analytical and Logical Reasoning questions like this

Analytical and Logical Reasoning is on 24 papers prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for every one of them.

Related questions