A dummy activity is used in PERT network to describe the_____________________?

Correct answer: B. Precedence relationship

  • A. Resource idleness
  • B. Precedence relationship
  • C. Resource restriction
  • D. Necessary time delay

Explanation

A dummy activity in PERT has zero duration and consumes no resources; it is inserted only to show the correct precedence relationship between activities. It therefore does not represent idleness or a time delay.

Written and checked by , MS Computer ScienceLast updated
Report an error

The more specific you are, the faster it gets fixed. A source beats an opinion.

Prefer email? [email protected]

Practise Plant Design and Economics

803 free Plant Design and Economics MCQs from Chemical Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.

Discussion

Stuck on an option, or know a faster way to get there? Ask or explain it here.

No comments yet. Be the first to explain this one.

Exams that ask Chemical Engineering questions like this

Chemical Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.

More Plant Design and Economics questions