Which one is not a risk management activity ?

Correct answer: B. Risk generation

  • A. Risk assessment
  • B. Risk generation
  • C. Risk control
  • D. None of the mentioned

Explanation

Risk assessment and risk control are recognized risk-management activities, whereas “risk generation” is not. Risk identification may reveal or generate a list of risks, but it is not called risk generation.