Which of the following process is concerned with analyzing the costs and benefits of proposed changes ?

Correct answer: A. Change management

  • A. Change management
  • B. Version management
  • C. System building
  • D. Release management

Explanation

Change management assesses proposed changes, including their effects, costs, and benefits, before approval. Version and release management track software states and deliveries rather than deciding whether a change is worthwhile.

Written and checked by , MS Computer ScienceLast updated
Report an error

The more specific you are, the faster it gets fixed. A source beats an opinion.

Prefer email? [email protected]

Practise Software Project Management

171 free Software Project Management MCQs from Software Engineering, each with the correct answer and an explanation. Unlimited attempts, no account needed.

Discussion

Stuck on an option, or know a faster way to get there? Ask or explain it here.

No comments yet. Be the first to explain this one.

Exams that ask Software Engineering questions like this

Software Engineering is on this paper prepared for on TestUstad, and all of them draw the same bank, so this question is worth knowing for it.

More Software Project Management questions